Should I consider the build order of a beMAX structure before I start building?

The beMAX structure is perfectly symmetrical, but some consideration is necessary to correctly position the crossbars in relation to any additional elements. 

It is generally advised to assemble the corner boxes to the horizontal beMAX beams first. Then, the preassembled horizontal beams can be installed onto the vertical beams.

          bemax sequence 1          bemax sequence 2

                       Correct building sequence                                   Wrong building sequence

 

Please note that additional beams of equal length cannot be attached inside a closed structure after assembly.